Town of Inlet: Construction of Coach’s Cabin continues on schedule

Construction of the new youth building at Arrowhead Park—the Coach’s Cabin—is moving along, thanks to a Local Waterfront Revitalization Project Grant administered through CAP-21, according to Inlet Town Clerk Patty Wittmeyer.

Wittmeyer reported that as of Wednesday, December 12, the insulation and the dry wall have been installed and the inside of the garage has been completed.

Garage doors are expected to be installed within the next two weeks.

However, she would like the public to know that the construction may cause a disruption to the lighting of Fern Park’s cross-country ski trails this winter.

Due to electrical usage for the project, night skiing on the trails may be delayed until sometime in February.